PJM raises Valley Link grid line cost to $5.1 billion and seeks faster data center hookups

The grid operator's board approved higher costs and later dates for two 765-kilovolt lines, two days after it asked federal regulators to halve the time to connect new power plants and large loads.

PermitQuant · 24 November 2026
PJM raises Valley Link grid line cost to $5.1 billion and seeks faster data center hookups
Illustration: PermitQuant

The board of PJM Interconnection, the regional grid operator, approved higher costs and later completion dates for some of its largest planned transmission projects on November 18 1. The biggest change is to Valley Link, two 765-kilovolt lines and related substations that would form a new west-to-east backbone across the PJM region. Its cost rose to $5.1 billion in 2026 dollars from about $3.0 billion in 2024 dollars 1.

Valley Link is being developed by Valley Link VA Inc., a venture of Transource, Dominion Energy and FirstEnergy 1. Its in-service dates moved from June 1, 2029, to between January 2030 and May 2031, depending on the facility 1. PJM cited higher construction labor and outside services, right-of-way and land, and material and equipment costs, and said routing analysis, stakeholder and regulatory work and permitting slowed the schedule 1.

The board also approved a $783 million increase, to $1.69 billion, for Exelon upgrades in Maryland that must be finished before the Brandon Shores and Wagner power plants can retire 1. PJM said higher utility labor rates, driven by workforce shortages, wage inflation and the volume of infrastructure work, pushed up the cost 1. Staff said "the underlying reliability needs have not changed" and that further delay would likely add cost 1.

Transmission cost changes approved by PJM's board, November 18, 2026
ProjectEarlier estimateNew estimateSchedule
Valley Link 765 kV lines (Valley Link VA Inc.)About $3.0 billion (2024 dollars)$5.1 billion (2026 dollars)Moved from June 2029 to January 2030-May 2031
Exelon Maryland upgrades-$1.69 billion (up $783 million)Needed before Brandon Shores and Wagner retire
Source: [1]

Faster connections for data centers

Two days earlier, PJM filed a "Fast Energization" proposal with the Federal Energy Regulatory Commission that it says would cut the projected time to study new generation and transmission service for large loads to one year from about two 2. The plan would study generation and load together, arrange interim transmission service for large loads while network upgrades are built, cover loads that bring their own generation or can cut demand, and impose earlier readiness and financial requirements to screen out speculative projects 2. It would also give states access to the costs of upgrades driven by data centers so they can bill those customers 2. PJM asked FERC for an order within 120 days 2.

A second filing the same day would create a category for large computational loads above 50 megawatts and require them to stay connected through voltage and frequency disturbances 3. PJM said nearly 3.9 gigawatts of data centers in the Dominion zone switched unexpectedly to onsite generators during a routine transmission disturbance on July 22, the largest such load transfer in its history 3. PJM serves about 10 gigawatts of such loads today and forecasts up to 30 gigawatts more by 2030 3. The rules would take effect January 16, 2027, with existing facilities given a year to comply 3.

PJMTransmissionData centersInfrastructureFERCPower
Sources
  1. PJM Inside Lines: PJM Board approves transmission project changes to support grid reliability
  2. PJM Inside Lines: PJM plan would cut interconnection process time in half
  3. PJM Inside Lines: PJM proposes new rules to protect grid reliability as data center demand grows
More news
Construction · 24 Nov

AECOM's backlog reaches a record $28 billion as fourth-quarter revenue falls 7%

Construction · 24 Nov

Buildings department proposes coded signs for basement and cellar ADUs

Construction · 24 Nov

Office and data center construction climbs 39.5% while factory spending falls 17.9%

Construction · 24 Nov

EMCOR's backlog reaches a record $18.6 billion as data center work doubles