Texas county declines to advance SpaceX tax break for $24 billion Starbase data center

Cameron County commissioners voted 3-2 against holding a public hearing on SpaceX's request for a 10-year, 100% property tax abatement on a planned data center and gas-fired power plant.

PermitQuant · 24 November 2026
Texas county declines to advance SpaceX tax break for $24 billion Starbase data center
Illustration: PermitQuant

Commissioners in Cameron County, Texas, voted 3-2 on November 17 against advancing SpaceX's request for a property tax break on a planned $24 billion data center and natural gas power plant at its Starbase complex near Boca Chica Beach 1,4. The company had asked for a 100% abatement of county property taxes for 10 years 1,2.

County Judge Eddie Treviño Jr. and Precinct 2 Commissioner Joey Lopez voted to move the request forward 1,4. Lopez said the vote was about holding a public hearing rather than approving the abatement, and that the request was effectively dead because there would be no second meeting 1,2.

What SpaceX wants to build

SpaceX's Starbase data center request
$24 billion
Cost of data center and gas plant, initial phase
10 years
Length of requested 100% abatement
444 acres
Project site
750 MW
Gas turbine output in state air permit
Source: [1]

The project would sit on a 444-acre site in the Cameron County Enterprise Zone, about 20 miles east of Brownsville 1. The $24 billion figure covers the initial phase, and the project could be expanded later 1,4. Wccftech reported that SpaceX applied for the abatement in mid-October, that its earlier county tax breaks ended in December 2025, and that the company plans a closed-loop cooling system, with construction scheduled to start in the fourth quarter of 2026 and finish by the second quarter of 2027 2. The site was removed from Brownsville's jurisdiction and annexed to the City of Starbase earlier this year 2.

Power would come from an on-site gas plant. Newsweek, citing POLITICO, reported that the Texas Commission on Environmental Quality approved an air permit the same week for 35 natural gas turbines producing 750 megawatts, allowing up to 248 tons of nitrogen oxides a year 1. The agency had paused data center permits in September on orders from Gov. Greg Abbott while the state grid operator, ERCOT, gathered data on grid impacts, and has since resumed normal reviews 1.

Company response

In a statement on November 18, SpaceX said expensive computing hardware loses value quickly, which could cause swings in local tax rates and a later drop in revenue, and that its proposal would have used payments in lieu of taxes instead 4. "The agreement was intended to provide more predictable County revenue while supporting continued investment in the region," the company said 4. It said it looked forward to "continued discussions with local jurisdictions on how to maximize the economic benefits of these investments" 3.

SpaceX had said that without the abatement it could put current or future investment into computing sites outside Cameron County 2. The company has not announced that the project is cancelled, and a separate incentive process with the City of Starbase is not affected by the county vote 4. The vote also lands as Texas politics shift: Democratic governor-elect Gina Hinojosa has pledged to halt data center approvals until lawmakers pass what she called "real protections" for Texans 1.

SpaceXData centersTexasCameron CountyTax abatementsPower plants
Sources
  1. Newsweek: Texas county blocks tax break for SpaceX data center
  2. Wccftech: SpaceX's tax break bid for its $24 billion Starbase data center quashed as commissioners vote against public hearing for 100% 10-year abatement
  3. Wccftech: SpaceX breaks silence, says 10-year 100% tax abatement for $24 billion Starbase data center infrastructure is necessary to avoid rapid tax value fluctuations
  4. Tesla North: SpaceX defends tax deal after county rejects data centre hearing
More news
Development · 24 Nov

Niron Magnetics picks Dothan, Alabama, for a $1.8 billion magnet plant with 700 jobs

Development · 24 Nov

Loudoun County pauses data center approvals while it rewrites its rules

Development · 24 Nov

NYC issues 16 office conversion permits since the Pfizer tower failure

Development · 24 Nov

Council committees advance five NYC rezonings with nearly 1,500 homes